当前位置:建设查建筑题库编辑工程项目施工组织设计时;一般将施工段的划分、施工顺序的安排列入施工组织设计的( )部分。

问题:

编辑工程项目施工组织设计时;一般将施工段的划分、施工顺序的安排列入施工组织设计的( )部分。

A.施工进度计划 B.施工总面积图 C.施工部署和施工方案 D.工程概况